This task will track the scheduling and swap out of the central mgmt switch in eqiad, msw1-eqiad.
Current msw1/ex4200: https://netbox.wikimedia.org/dcim/devices/50/
Future msw1-EX4300: https://netbox.wikimedia.org/dcim/devices/2269/
The [[ https://netbox.wikimedia.org/dcim/devices/50/ | old/existing switch is an EX4200 ]], and will be replaced with the [[ https://netbox.wikimedia.org/dcim/devices/2269/ | new EX4300 ordered on T221883 ]].
Items to confirm/update:
[x] - netops confirms on task if they want new EX4300 racked for configuration in advance of migration
[] - migration window is scheduled
[x] - racking and labeling of EX4300 (pending answer if this needs racking prior to migration, or if it can just go where existing EX4200 is presently.)
[x] - configuration of EX4300
[] - migration of cables from EX4200 to EX4300
[] - wipe/decommission old [[ https://netbox.wikimedia.org/dcim/devices/50/ | EX4200 ]]
[] - test ALL mgmt uplinks by connecting to one server in every rack.