Validate data quality of Phlogiston
Closed, ResolvedPublic

Description

Validate that the Phlogiston reports are accurate, especially the data used for forecasting.

  • Could do this by comparing to Phragile reports.
  • Could also create a known data set and then reporting on it. If we did this, then we could be sure Phlogiston was correct and use it to validate Phragile. - CUT and SPIN OFF

Event Timeline

JAufrecht raised the priority of this task from to Medium.
JAufrecht updated the task description. (Show Details)
JAufrecht added a project: Team-Practices.
JAufrecht subscribed.

Notes from spot comparison of Phlogiston and Phragile spot:

Discrepencies:
Phragile's scope line doesn't start until mid-August. This is because Phragile does a nightly snapshot, rather than reconstruction, for scope, and Kevin associated Phragile with this project in mid-August.

Phragile burnup shows a spike today that is not in Phlogiston. This is because Phlogiston is running from a nightly dump.

Phragile scope line extends backwards and forwards to the end of the chart, but this does not represent data; this is just an extension of the edge values.

Phragile's burnup line is a historical reconstruction of point totals, but working from a list of tasks belonging to the project today. So if you remove a task from the project on Tuesday, on Wednesday Phragile's burnup will not show that task at any point, whereas Phlogiston's burnup will show that task up until Tuesday.

discovery_comparison.png (592×2 px, 105 KB)

JAufrecht set Security to None.
JAufrecht moved this task from To Do to Done on the Team-Practices (This-Week) board.
JAufrecht updated the task description. (Show Details)