Page MenuHomePhabricator

Rack/cable/configure mr1-eqiad
Closed, DuplicatePublic

Description

Follow up from T180414:

  • Rack the new srx220 (Chris)
  • Connect console (Chris)
  • Connect a USB drive with install1002:/srv/junos/junos-srxsme-12.3X48-D50.6-domestic.tgz and copy of existing conf (Chris)
  • Configure new device (Arzhel)

In a window:

  • Downtime device (Arzhel)
  • Do a 1:1 move of cables from old to new SRX (Chris)
  • Verify device & monitoring is happy
  • Wipe/unrack old srx
  • update inventory

Event Timeline

ayounsi triaged this task as Medium priority.Feb 20 2018, 6:47 PM
ayounsi created this task.