This task will track the racking, setup, and installation of the 4 new dbproxy hosts received in T213766.
Rack proposal:
- dbproxy2001 on row A rack A6 U9
- dbproxy2002 on row B rack B6 U4
- dbproxy2003 on row C rack C6 U15
- dbproxy2004 on row D rack D6 U43
dbproxy2001: A6 ge-6/0/8
- - receive in system on procurement task T213766
- - rack system with proposed racking plan (see above) & update netbox (include all system info plus location)
- - bios/drac/serial setup/testing
- - No RAID controller ( Please provide SW RAID to use)
- - mgmt dns entries added for both asset tag and hostname
- - network port setup
- end on-site specific steps
- - production dns entries
- - operations/puppet update (install_server at minimum, other files if possible)
- - OS installation (stretch) - update netbox status to staged
- - puppet accept/initial run
- - handoff for service implementation - service implementation team must change status from staged to active
dbproxy2002: B6 ge-6/0/3
- - receive in system on procurement task T213766
- - rack system with proposed racking plan (see above) & update netbox (include all system info plus location)
- - bios/drac/serial setup/testing
- - No RAID controller ( Please provide SW RAID to use)
- - mgmt dns entries added for both asset tag and hostname
- - network port setup
- end on-site specific steps
- - production dns entries
- - operations/puppet update (install_server at minimum, other files if possible)
- - OS installation (stretch) - update netbox status to staged
- - puppet accept/initial run
- - handoff for service implementation - service implementation team must change status from staged to active
dbproxy2003: C6 ge-6/0/9
- - receive in system on procurement task T213766
- - rack system with proposed racking plan (see above) & update netbox (include all system info plus location)
- - bios/drac/serial setup/testing
- - No RAID controller ( Please provide SW RAID to use)
- - mgmt dns entries added for both asset tag and hostname
- - network port setup
- end on-site specific steps
- - production dns entries
- - operations/puppet update (install_server at minimum, other files if possible)
- - OS installation (stretch) - update netbox status to staged
- - puppet accept/initial run
- - handoff for service implementation - service implementation team must change status from staged to active
dbproxy2004: D6 ge-6/0/20
- - receive in system on procurement task T213766
- - rack system with proposed racking plan (see above) & update netbox (include all system info plus location)
- - bios/drac/serial setup/testing
- - No RAID controller ( Please provide SW RAID to use)
- - mgmt dns entries added for both asset tag and hostname
- - network port setup
- end on-site specific steps
- - production dns entries
- - operations/puppet update (install_server at minimum, other files if possible)
- - OS installation (stretch) - update netbox status to staged
- - puppet accept/initial run
- - handoff for service implementation - service implementation team must change status from staged to active