This task is to track blockers and rollout timeline for Special:Investigate

Timeline
  • 10 August: Deploy to French Wikipedia
  • 11 August - 14 Sept: QA testing + Collect feedback from checkusers
  • 14 September: Deploy on Spanish wiki
  • 24 September: Deploy on Italian and Swedish wikis
  • 24 September - TBD: Next round of feedback gathering
  • 8 October: Deploy everywhere
Blockers
  1. T258616: CU 2.0: Add an overlay to the GuidedTour (in QA)
  2. T259032: Pager queries are performed twice when Special:Investigate forms are submitted (in QA)
  3. T255688: Instrument Special:Investigate using EventLogging (in QA)
  4. T256586: Special:Investigate: Onboarding: Restart tour and help links
  5. T259079: Add link from old checkuser page to the new one on wikis where the new page is deployed

Event Timeline

Niharika triaged this task as Medium priority.

Hello! I'm sure something has happened that prevented the rollout everywhere on Aug., 25 as planned. Could I ask for a status update? Thanks!

@MarcoAurelio Thanks for the question. During some final QA and user testing in the second phase outline above there were some bugs and suggestions that seemed important to address before we get this in front of more users. Given the sensitivity of the feature and the data within the tool, we want to to be cautious with any potential issues. Combining that with a few weeks that didn't have train releases and the project is delayed as you've noticed.

We should be able to have something out very soon.

Thanks for the reply @aezell - Sounds sensible to me to delay if the feature was not yet ready. Thanks all for your work.

@MarcoAurelio My bad - I didn't update the timeline. We decided to release the feature to some more selective wikis before we do a wider launch because we haven't received as much feedback as we liked.

Niharika claimed this task.