From context on T274171 it seems we need to decom all codfw appservers purchased on 2016-05-17.
Is this right?
That is currently 28 boxes reported by netbox. It does not match exactly the procurement task T134272 though.
- mw2215
- mw2216
- mw2217
- mw2218
- mw2219
- mw2220
- mw2221
- mw2222
- mw2223
- mw2224
- mw2225
- mw2226
- mw2227
- mw2228
- mw2229
- mw2230
- mw2231
- mw2232
- mw2233
- mw2234
- mw2235
- mw2236
- mw2237
- mw2238
- mw2239
- mw2240
- mw2241
- mw2242
I do not want to repeat the same template 28 times on this ticket to end up with hundreds of checkboxes, but we need to follow the server lifecycle page anyways.