Formalize rollout plan
Closed, ResolvedPublic0 Estimated Story Points

Description

Steph and Olga work out what the rollout plan for the donate A/B test should be, then run it by the SDS folks

The approved rollout plan is:
Stage 0 - code is rolled out to beta/prod and by default nobody is in the experiment
Stage 1 - Experiment is created in xLab - Testwiki 5/5, English Wikipedia 0/0
Stage 2 - English Wikipedia .05/.05

Event Timeline

SToyofuku-WMF moved this task from Incoming to Q4 on the Web-Team board.
SToyofuku-WMF set the point value for this task to 0.

My vision is this will be a zero pointer, but reflect the work Olga and I will be doing behind the scenes to figure out how we're going to safely test all paths before launching this experiment

Proposed rollout plan discussed with Olga:
Stage 0 - code is rolled out to beta/prod and nobody is in the experiment, experiment is created in xLab with testwiki at 0% and enwiki at 0%
Stage .5 - Beta 50/50
Stage 1 - Testwiki 50/50, English Wikipedia 0/0
Stage 2 - English Wikipedia target/target <- still need to get this number

Next steps finalize the target for enwiki and double check with experiment platform team about xLab capabilities

SToyofuku-WMF moved this task from Q4 to Sprint Backlog on the Web-Team board.

Perhaps a more controversial priority, but all are subject to change

JScherer-WMF lowered the priority of this task from High to Medium.Jun 18 2025, 5:22 PM

Newest plan proposed:
Stage 0 - code is rolled out to beta/prod and by default nobody is in the experiment
Stage .5 - Beta 10/10
Stage 1 - Experiment is created in xLab - Testwiki 10/10, English Wikipedia 0/0
Stage 2 - English Wikipedia .05/.05

I misunderstood the 10% figure:
Stage 0 - code is rolled out to beta/prod and by default nobody is in the experiment
Stage .5 - Beta 5/5
Stage 1 - Experiment is created in xLab - Testwiki 5/5, English Wikipedia 0/0
Stage 2 - English Wikipedia .05/.05

Will double check this before finalizing, then we can add dates when we get closer to finishing the development tasks

Do you mind certifying that this rollout plan is indeed what we all agreed to?

Resolving. Rollout plan is now ready

Noting we're skipping Stage .5 since we can use URL parameters on beta