Experiment plan for Article Guidance
Closed, ResolvedPublic4 Estimated Story Points

Description

As part of Article Guidance (T396029) first intervention, we plan to help junior editors when they try to create an article. The intervention is an experiment we want to support using A/B testing.

This ticket covers the experiment plan and preparations. Based on the proposed workflow (T414409) and the metrics defined (T414503), we will design the experiment and complete all preparations so it is ready to launch as soon as the feature is ready. The goal is to prepare the experiment in advance of the product implementation to avoid unnecessary delays.

Hypothesis

If we prepare an A/B test experiment, including how to expose the new feature (entry points) and how to measure the impact (metrics), we'll be ready to start learning about the impact of Article Guidance on the survival rate of articles created by junior editors on mobile.

Decision to be made

Are all of the following true before we start the experiment?

  1. The guided article creation flow is instrumented and the instrumentation has been QA'd
  2. The experiment is configured in Test Kitchen and has passed security review
  3. The outlines have been reviewed and approved by pilot wiki communities
  4. The entry points are defined and technically implemented
  5. The measurement plan has been signed off by all stakeholders
  6. Sample size and statistical power have been calculated
  7. The edit tag for tracking articles created via the intervention is implemented
  8. The workflow is localised into all pilot wiki languages

Deployment timing

MilestoneTarget dateTicketResponsibleStatusNotes
EXPERIMENT PLANNING
Measurement plan drafted and signed offMar 2026 (W.11)T414503@GGalofre-WMFIN PROGRESSDrafted and shared with @JVanderhoop-WMF and @MNeisler
Entry point analysis completeW.14T416686@MNeislerIN PROGRESSDelivering W.14
Sample size and power calculation completeW.14T414536@MNeislerIN PROGRESSRunning W.14. Feeds into measurement plan sign-off
INSTRUMENTATION & TECHNICAL IMPLEMENTATION
Feature implementation completeW.13T414409@SBisson / @eamedinaTo review with Pau in Week 12
Instrumentation spec complete and QA'dW.12T417046@MNeislerOn critical path, needs to start this week. See Experimentation Checklist - Instrumentation section
Security review completeW.13T418724@NikerabbitSee Experimentation Checklist - Instrumentation section
Edit tag implementedW.13T418155@SBisson / @eamedinaDONE
Feature flag, variation assignment and data collection implementedW.13T410569@SBisson / @eamedina⚠️ At risk - detailed specs needed urgently for this to be achievable in W.13. See Experimentation Checklist - Technical Implementation section
Experiment config and schemaW.14TBD@SBissonIN PROGRESSNew task to be created
Deploy on test wikiW.14T417200@SBisson / @eamedinaNeeds feature implementation and instrumentation QA done first. See Experimentation Checklist - Technical Implementation section
COMMUNITY
Outlines v1 definedW.12T417249@Pginer-WMF / @GGalofre-WMFDONE
Wikidata labels checked for pilot wiki topicsW.12T416986@Pginer-WMF / @GGalofre-WMFRuns in parallel with outlines
Workflow localised into all pilot wiki languagesW.14@Pginer-WMF / @GGalofre-WMFIN PROGRESSIncludes UI translation in TWN. Needed before patch demo so communities can edit outlines in their language
Patch demo tested by pilot communities (English)W.14–W.16T414448@UOzurumbaIN PROGRESSCommunication drafted W.14. Communities test workflow in patch demo in English and provide feedback. Feedback deadline: April 15 (W.16)
Outlines translated by pilot communitiesW.16–W.18@UOzurumbaIN PROGRESSAfter English patch demo feedback closes. Communities translate outlines into their languages. Must be complete before experiment launch. ~15 days
EXPERIMENTATION SETUP & PRE-LAUNCH
Experiment configured in Test KitchenW.14T414536@GGalofre-WMFSee Experimentation Checklist - Experimentation Setup section
Monitoring dashboard set up in SupersetW.14T414536@MNeislerSee Experimentation Checklist - Experimentation Setup section
Small-scale test and rollback plan completeW.15T410569@SBissonNeeds deploy on test wiki done first. See Experimentation Checklist - Pre-Launch Verification section
Final review with all stakeholders completeW.15T414536@Pginer-WMF / @GGalofre-WMFFull review of current state and remaining decisions. See Experimentation Checklist - Pre-Launch Verification section
Final sign-off obtained (SRE, Data Products)W.15@Pginer-WMF / @GGalofre-WMFSee Experimentation Checklist - Launch section
Ready to start experimentW.18T396029@Pginer-WMF / @GGalofre-WMFDependent on outline translation by pilot communities completing by end of W.18

Critical path

Two parallel tracks converge at deploy on test wiki:

Track 1 - Instrumentation:
Instrumentation spec (W.12) -> Security review (W.13) -> Instrumentation implementation and QA (W.13) -> Deploy on test wiki (W.14)

Track 2 - Feature code (already in progress):
Feature implementation (W.13) -> Experiment config and schema (W.14) -> Deploy on test wiki (W.14)

From W.14 onwards:
Deploy on test wiki (W.14) -> Small-scale test (W.15) -> Final review and sign-off (W.15) -> Community outline translation (W.16–W.18) -> Launch (W.18)

⚠️ Note: the critical path now runs through community outline translation, which cannot begin until the English patch demo feedback window closes on April 15 (W.16) and then requires approximately 15 days for communities to translate outlines. Any delay in the patch demo feedback cycle or translation will push the launch date beyond W.18. The full team review scheduled for W.15 will be a key checkpoint to assess whether the launch date is still achievable.

Dependencies

MilestoneDepends on
Security reviewInstrumentation spec complete
Instrumentation implementation and QAInstrumentation spec complete, security review complete
Deploy on test wikiFeature implementation complete, instrumentation QA complete
Patch demo tested by pilot communities (English)Outlines v1 defined, Wikidata labels checked, workflow localised
Outlines translated by pilot communitiesEnglish patch demo feedback complete (deadline April 15 / W.16)
Experiment configured in Test KitchenEntry point analysis complete, sample size calculation complete
Monitoring dashboard set up in SupersetExperiment configured in Test Kitchen
Small-scale test and rollback plan completeDeploy on test wiki
Final review with all stakeholders completeSmall-scale test complete, patch demo complete, monitoring dashboard set up
Final sign-off obtainedFinal review complete
Ready to start experimentFinal sign-off obtained, outline translation complete

Quit criteria

We would consider stopping work on guided article creation entirely if the Q4 experiment shows both of the following:

  1. No statistically significant improvement in 30-day survival rate in the treatment group compared to the control group, across all pilot wikis
  2. A meaningful increase in abandonment rate, indicating the workflow is acting as a barrier rather than an enabler

If only one of these is true, we iterate rather than stop. If both are true, the evidence suggests the approach is neither helping editors succeed nor encouraging them to try, and we would reassess the direction entirely.

Q4 Experiment Decision Matrix

ScenarioIndicatorsAction
1Survival rate improves significantly AND abandonment rate stays the same or decreases AND total surviving articles stays the same or increasesScale. Roll out to additional wikis. Proceed with OW1.4 scaling plan. Consider expanding entry points and testing in-VE guidance.
2Survival rate improves significantly BUT abandonment rate increases meaningfullyIterate before scaling. The guidance is helping article quality but creating friction. Identify and remove funnel steps causing drop-off before wider rollout.
3Survival rate improves significantly BUT total surviving articles decreasesIterate before scaling. The guidance is helping quality but acting as a barrier to creation. Reduce friction in the workflow before wider rollout.
4Survival rate improves significantly on some pilot wikis but not othersIterate before scaling. Analyse what differs between wikis where the guidance worked and where it did not. Consider whether guidance accuracy, article type coverage, or localisation are contributing factors before wider rollout.
5No statistically significant impact on survival rate AND abandonment rate stays neutralIterate and retest. The guidance is not yet effective enough overall, but funnel drop-off data may reveal a specific step responsible for most exits. Address that step and retest rather than rethinking the whole workflow.
6No statistically significant impact on survival rate AND abandonment rate increases meaningfullyStop or fundamentally rethink. This is the quit criteria scenario. The workflow is a barrier and not helping. Reassess the approach before any further investment.
7Results are inconclusive due to insufficient sample size or experiment durationExtend or rerun. Adjust experiment parameters and rerun before making a scaling decision.