Page MenuHomePhabricator

Q1:rack/setup/install apus-be100[7-9]
Open, MediumPublic

Description

This task will track the racking, setup, and OS installation of X

Hostname / Racking / Installation Details

Hostnames: apus-be100[7-9]
Racking Proposal: Avoid existing backends i.e. not C4,D4,E8,F3
Networking Setup: # of Connections:1- Speed:10G. - VLAN:Private
OS Distro: bookworm
Boot Method: UEFI
Disks: JBOD
Sub-team Technical Contact: @MatthewVernon

Per host setup checklist

Each host should have its own setup checklist copied and pasted into the list below.

apus-be1007
  • Receive in system on procurement task T428109 & in Coupa
  • Rack system with proposed racking plan (see above) & update Netbox (include all system info plus location, state of planned)
  • Run the Provision a server's network attributes Netbox script - Note that you must run the DNS and Provision cookbook after completing this step
  • Immediately run the sre.dns.netbox cookbook
  • Immediately run the sre.hosts.provision cookbook
  • Run the sre.hardware.upgrade-firmware cookbook
  • Update the operations/puppet repo - this should include updates to preseed.yaml, and site.pp with roles defined by service group: https://wikitech.wikimedia.org/wiki/SRE/Dc-operations
  • Run the sre.hosts.reimage cookbook
apus-be1008
  • Receive in system on procurement task T428109 & in Coupa
  • Rack system with proposed racking plan (see above) & update Netbox (include all system info plus location, state of planned)
  • Run the Provision a server's network attributes Netbox script - Note that you must run the DNS and Provision cookbook after completing this step
  • Immediately run the sre.dns.netbox cookbook
  • Immediately run the sre.hosts.provision cookbook
  • Run the sre.hardware.upgrade-firmware cookbook
  • Update the operations/puppet repo - this should include updates to preseed.yaml, and site.pp with roles defined by service group: https://wikitech.wikimedia.org/wiki/SRE/Dc-operations
  • Run the sre.hosts.reimage cookbook
apus-be1009
  • Receive in system on procurement task T428109 & in Coupa
  • Rack system with proposed racking plan (see above) & update Netbox (include all system info plus location, state of planned)
  • Run the Provision a server's network attributes Netbox script - Note that you must run the DNS and Provision cookbook after completing this step
  • Immediately run the sre.dns.netbox cookbook
  • Immediately run the sre.hosts.provision cookbook
  • Run the sre.hardware.upgrade-firmware cookbook
  • Update the operations/puppet repo - this should include updates to preseed.yaml, and site.pp with roles defined by service group: https://wikitech.wikimedia.org/wiki/SRE/Dc-operations
  • Run the sre.hosts.reimage cookbook

Related Objects

StatusSubtypeAssignedTask
OpenMatthewVernon

Event Timeline

RobH assigned this task to MatthewVernon.
RobH mentioned this in Unknown Object (Task).
RobH added a parent task: Unknown Object (Task).
RobH moved this task from Backlog to Racking Tasks on the ops-eqiad board.
RobH unsubscribed.

Please update the site.pp file with the insetup role for your team (detailed on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations) and add the new servers to preseed.yml for partition info.

If possible, please reference this task number in your patch set, so it is clear when complete. Once complete, just un-assign yourself (leaving no assignee) for this task and once the hardware arrives on-site engineerss will claim this task for racking and setup. Please don't re-subscribe me to this task unless there is a direct question for me.

Thank you!

@cmooney I have these three servers I'd like to rack in A3, B3, and C1 using the new Nokia switches. If you have any concerns, let me know. Otherwise, I'll plan to rack them next week, if that works for you.

@cmooney I have these three servers I'd like to rack in A3, B3, and C1 using the new Nokia switches. If you have any concerns, let me know. Otherwise, I'll plan to rack them next week, if that works for you.

A3 and B3 aren't ready for servers right now, so depends when they need to go live. Probably by the end of next week they will be, so unless they are super urgent should be ok.

C1 is good to go immediately.

@cmooney I have these three servers I'd like to rack in A3, B3, and C1 using the new Nokia switches. If you have any concerns, let me know. Otherwise, I'll plan to rack them next week, if that works for you.

A3 and B3 aren't ready for servers right now, so depends when they need to go live. Probably by the end of next week they will be, so unless they are super urgent should be ok.

C1 is good to go immediately.

I'm currently blocked by power limitations in the existing 10G racks, so I don't think there's any urgency to get these servers turned over right away. Waiting a few weeks shouldn't have any impact, and it would give us a good opportunity to test the new Nokia switches.

Unable to install the rails they are too long and prevent the rack doors from closing.