After a conversation with @elukey I was advised to create this task to find the correct windows to build the page_change SLOs (draft doc) and understand how Sloth would handle them.
Completeness SLO:
This SLI is computed monthly, so a sensible window is a rolling 12 months. The intent is to give downstream users confidence that there have been ~11 consecutive months of correct execution (i.e. the budget tolerates one bad month per year).
Freshness SLO:
The proposed window is a rolling quarter (3 months). It measures how many events arrive late in the stream (similar to how many responses miss their deadline in a web-server latency SLO).
The goal is to have all the graphs and alerts together in one Grafana page, and trigger an alarm whenever either of the two starts burning through its error budget.
Open questions:
How would Sloth manage the 12 months window?
Would a 1-month rolling window for freshness fit Sloth's behaviour better?