- Detailed plan almost agreed with mentors: T92929
- Phabricator project created: Translation-search T97825
- Meetings with mentors started: The meeting was held on 2nd May to plan the detailed timeline. It was agreed that the regular meeting would be held every week after 30th May.
- Bonding period report published: T99648
Description
Description
Status | Subtype | Assigned | Task | ||
---|---|---|---|---|---|
Resolved | Qgil | T102790 Engineering Community quarterly review (as part of the Community Engagement review) | |||
Resolved | Qgil | T93770 Engineering Community quarterly goals for April-June 2015 | |||
Resolved | Niharika | T94166 Goal: Successful start of all GSoC / Outreachy projects | |||
Invalid | None | T89103 One stop translation search | |||
Resolved | Phoenix303 | T92929 Reinvent Translation Search | |||
Resolved | Nikerabbit | T97774 Community bonding evaluation for Reinvent Translation Search | |||
Resolved | Nemo_bis | T99648 Bonding period report for Reinvent Translation Search |
Event Timeline
Comment Actions
I think the bonding period report can easily be written; it's a huge PASS thanks to the conversations you had with translators and the several patches submitted and merged. Just let the links speak for you. :)
Comment Actions
Yay @Phoenix303, everything looks great! @Nemo_bis, @Nikerabbit, evaluate and close as appropriate.
Comment Actions
I'm going to close this because the plan has most required pieces now, but they'll need to be rearranged. More on the respective task.