Split of from T241852.
Of the remaining 20 nodes left from T241852, 10 need to become kubernetes hosts. Those will be kubernetes20[07-14].codfw.wmnet and kubestage200[1-2].codfw.wmnet.
Racking proposals:
**kubernetes20[07-14].codfw.wmnet**
Those are 1G hosts. We want 2 per rack row, racks themselves are utterly unimportant, feel free to pick whatever rack suits you best.
kubernetes2007 Rack A6U21 ge-6/023
kubernetes2008 Rack A6U29 ge-6/013
kubernetes2009 Rack B6U17
kubernetes2010 Rack B6U18
kubernetes2011 Rack C1U29
kubernetes2012 Rack C1U30
kubernetes2013 Rack D6U2
kubernetes2014 Rack D6U3
**kubestage200[1-2].codfw.wmnet ** Rack A1U28 and rack B1U5
Those are 1G hosts as well. 1 in row A and row B, whatever rack suits you best.
kubestage2001 Rack A1U28 ge-1/0/2
kubestage2002 Rack B1U5 ge-1/0/21
[x] - receive in system on #procurement task T231255
[] - rack system with proposed racking plan (see above) & update netbox (include all system info plus location, state of planned)
[] - bios/drac/serial setup/testing :
[] - mgmt dns entries added for both asset tag and hostname
[] - network port setup (description, enable, vlan)
** end on-site specific steps
[] - production dns entries added
[] - operations/puppet update (install_server at minimum, other files if possible)
[] - OS installation
[] - puppet accept/initial run (with role:spare)
[] - host state in netbox set to staged
[] - handoff for service implementation
[] - service implementer changes from 'staged' status to 'active' status in netbox'