This task will track the racking, setup, installation, and deployment of new labsdb1009, labsdb1010, & labsdb1011. These hosts were ordered on T135529.
These are HP DL380e systems, at 2U each. The current restriction is these will need to reside in the labs-support vlan. In eqiad, we only have that vlan deployed/allocated for us in rows A and C. A5 has some space, while C4 and C5 each have space. @cmjohnson may know of other issues that I'm (@robh) unaware of, and modify the racking assignment.
labsdb1009
[] - receive in normally via T135529
[] - rack in A5
[] - bios and ilom setup
[] - hw raid setup (raid10 of all disks)
[] - network port setup (description/enable/labs support vlan)
[] - update dns records (mgmt and production)
[] - update install_server module (Jessie, db partition recipe for hw raid)
[] - install OS
[] - accept/sign puppet/salt keys
[] - service implementation
labsdb1010
[] - receive in normally via T135529
[] - rack in C4
[] - bios and ilom setup
[] - hw raid setup (raid10 of all disks)
[] - network port setup (description/enable/labs support vlan)
[] - update dns records (mgmt and production)
[] - update install_server module (Jessie, db partition recipe for hw raid)
[] - install OS
[] - accept/sign puppet/salt keys
[] - service implementation
labsdb1011
[] - receive in normally via T135529
[] - rack in C5
[] - bios and ilom setup
[] - hw raid setup (raid10 of all disks)
[] - network port setup (description/enable/labs support vlan)
[] - update dns records (mgmt and production)
[] - update install_server module (Jessie, db partition recipe for hw raid)
[] - install OS
[] - accept/sign puppet/salt keys
[] - service implementation