This task will track the racking of the 32 new PDUs into the new eqiad row expansion.
8 cabinets of C2[LS]42CE-YCMFAM00 & 8 cabinets of C2[LS]54CE-YCMFA900 along with (16) PDU mounting brackets for Rittal racks.
The new row will likely be row E [1-8] and F [1-8] or just E [1-16].
The first 8 cabinets will get the C2[LS]42CE-YCMFAM00, the other 8 will get the C2[LS]54CE-YCMFA900 when they arrive in November.
Please note we aren't allowed to energize the PDUs, and must open a smart hands ticket with DC6 staff to do so. Once all 8 of the first racks are staged, a single ticket can be opened to have all 8 energized/plugged in.
Rack E1:
[] - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
[] - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
[] - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
[] - connect PDU to serial console server
[] - open ticket for PDUs to be plugged in / energized once racks E[1-8] are ready.
[x] - confirm PDU energized for setup
[x] - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech
Rack E2:
[] - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
[] - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
[] - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
[] - connect PDU to serial console server
[] - open ticket for PDUs to be plugged in / energized once racks E[1-8] are ready.
[x] - confirm PDU energized for setup
[x] - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech
Rack E3:
[] - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
[] - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
[] - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
[] - connect PDU to serial console server
[] - open ticket for PDUs to be plugged in / energized once racks E[1-8] are ready.
[x] - confirm PDU energized for setup
[x] - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech
Rack E4:
[] - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
[] - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
[] - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
[] - connect PDU to serial console server
[] - open ticket for PDUs to be plugged in / energized once racks E[1-8] are ready.
[x] - confirm PDU energized for setup
[x] - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech
Rack E5:
[] - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
[] - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
[] - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
[] - connect PDU to serial console server
[] - open ticket for PDUs to be plugged in / energized once racks E[1-8] are ready.
[] - confirm PDU energized for setup
[] - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech
Rack E6:
[] - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
[] - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
[] - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
[] - connect PDU to serial console server
[] - open ticket for PDUs to be plugged in / energized once racks E[1-8] are ready.
[] - confirm PDU energized for setup
[] - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech
Rack E7:
[] - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
[] - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
[] - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
[] - connect PDU to serial console server
[] - open ticket for PDUs to be plugged in / energized once racks E[1-8] are ready.
[] - confirm PDU energized for setup
[] - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech
Rack E8:
[] - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
[] - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
[] - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
[] - connect PDU to serial console server
[] - open ticket for PDUs to be plugged in / energized once racks E[1-8] are ready.
[] - confirm PDU energized for setup
[] - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech
Rack F1:
[] - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
[] - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
[] - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
[] - connect PDU to serial console server
[] - open ticket for PDUs to be plugged in / energized once racks E[9-16]/F[1-8] are ready.
[] - confirm PDU energized for setup
[] - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech
Rack F2:
[] - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
[] - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
[] - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
[] - connect PDU to serial console server
[] - open ticket for PDUs to be plugged in / energized once racks E[9-16]/F[1-8] are ready.
[] - confirm PDU energized for setup
[] - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech
Rack F3:
[] - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
[] - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
[] - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
[] - connect PDU to serial console server
[] - open ticket for PDUs to be plugged in / energized once racks E[9-16]/F[1-8] are ready.
[] - confirm PDU energized for setup
[] - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech
Rack F4:
[] - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
[] - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
[] - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
[] - connect PDU to serial console server
[] - open ticket for PDUs to be plugged in / energized once racks E[9-16]/F[1-8] are ready.
[] - confirm PDU energized for setup
[] - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech
Rack F5:
[] - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
[] - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
[] - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
[] - connect PDU to serial console server
[] - open ticket for PDUs to be plugged in / energized once racks E[9-16]/F[1-8] are ready.
[] - confirm PDU energized for setup
[] - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech
Rack F6
[] - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
[] - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
[] - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
[] - connect PDU to serial console server
[] - open ticket for PDUs to be plugged in / energized once racks E[9-16]/F[1-8] are ready.
[] - confirm PDU energized for setup
[] - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech
Rack F7:
[] - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
[] - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
[] - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
[] - connect PDU to serial console server
[] - open ticket for PDUs to be plugged in / energized once racks E[9-16]/F[1-8] are ready.
[] - confirm PDU energized for setup
[] - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech
Rack F8:
[] - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
[] - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
[] - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
[] - connect PDU to serial console server
[] - open ticket for PDUs to be plugged in / energized once racks E[9-16]/F[1-8] are ready.
[] - confirm PDU energized for setup
[] - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech