This task will track the receiving, racking, setup, and installation of LVS200[7-10]
Racking proposal
| servers | Rack |NIC1|NIC2|NIC3|NIC4|
|LVS2007|A2|asw-a2|asw-b2|asw-c2|asw-d2|
|LVS2008|B2|asw-b2|asw-a2|asw-c2|asw-d2|
|LVS2009|C2|asw-c2|asw-a2|asw-b2|asw-d2|
|LVS2010|D2|asw-d2|asw-a2|asw-b2|asw-c2|
@BBlack since lvs2007 will be racked in the same rack as Lvs200[1-3] and lvs2008 in the same rack as lvs200[4-6] I can re-use the cables/fibers off one of the old LVS if we decommission one of them and for lvs2009 and lvs2010, I can pull new cables/fibers. Let me know what you think.
LVS2007:
[x] - receive in system on procurement task T193820
[x] - rack system with proposed racking plan (see above) & update racktables (include all system info plus location)
[x] - bios/drac/serial setup/testing
[x] - mgmt dns entries added for both asset tag and hostname
[] - network port setup (description, enable, vlan)
end on-site specific steps
[x] - production dns entries added
[] - operations/puppet update (install_server at minimum, other files if possible)
[] - OS installation
[] - puppet accept/initial run
[] - handoff for service implementation
LVS2008:
[x] - receive in system on procurement task T193820
[x] - rack system with proposed racking plan (see above) & update racktables (include all system info plus location)
[x] - bios/drac/serial setup/testing
[x] - mgmt dns entries added for both asset tag and hostname
[] - network port setup (description, enable, vlan)
end on-site specific steps
[x] - production dns entries added
[] - operations/puppet update (install_server at minimum, other files if possible)
[] - OS installation
[] - puppet accept/initial run
[] - handoff for service implementation
LVS2009:
[x] - receive in system on procurement task T193820
[x] - rack system with proposed racking plan (see above) & update racktables (include all system info plus location)
[x] - bios/drac/serial setup/testing
[x] - mgmt dns entries added for both asset tag and hostname
[x] - network port setup (description, enable, vlan)
end on-site specific steps
[x] - production dns entries added
[x] - operations/puppet update (install_server at minimum, other files if possible)
[x] - OS installation
[x] - puppet accept/initial run
[] - handoff for service implementation
LVS2010:
[x] - receive in system on procurement task T193820
[x] - rack system with proposed racking plan (see above) & update racktables (include all system info plus location)
[x] - bios/drac/serial setup/testing
[x] - mgmt dns entries added for both asset tag and hostname
[x] - network port setup (description, enable, vlan)
end on-site specific steps
[x] - production dns entries added
[x] - operations/puppet update (install_server at minimum, other files if possible)
[x] - OS installation
[x] - puppet accept/initial run
[] - handoff for service implementation
Wiring progress
|server|NIC1|NIC2|NIC3|NIC4|
|lvs2007||||||||
|lvs2008||||||||
|lvs2009|complete|complete|complete|complete|
|lvs2010|complete|complete|complete|complete|