This task will track the migration of the ps1 and ps2 to be replaced with new PDUs in rack [[ https://netbox.wikimedia.org/dcim/racks/2/ | A2-eqiad ]].
Each server & switch will need to have potential downtime scheduled, since this will be a live power change of the PDU towers.
These racks have a single tower for the old PDU (with and A and B side), with the new PDUs having independent A and B towers.
[] - schedule downtime for the entire list of switches and servers.
[] - Wire up one of the two towers, energize, and relocate power to it from existing/old pdu tower (now de-energized).
[] - confirm entire list of switches, routers, and servers have had their power restored from the new pdu tower
[] - Once new PDU tower is confirmed online, move on to next steps.
[] - Wire up remaining tower, energize, and relocate power to it from existing/old pdu tower (now de-energized).
[] - confirm entire list of switches, routers, and servers have had their power restored from the new pdu tower
== List of routers, switches, and servers ==
| device | role | SRE team coordination
| asw2-a2-eqiad | asw | @ayounsi
| conf1001 |
| kafka1023 | kafka | #analytics
| kafka1013 | kafka | #analytics
| kafka1012 | kafka | #analytics
| db1107 | db | #dba
| tungsten |
| cloudelastic1001 | | #cloud-services-team
| kafka-jumbo1002 | kafka | #analytics
| ms-be1045 | ms-be |
| ms-be1044 | ms-be |
| an-worker1079 | analytics | #analytics
| db1082 | db | #dba
| db1081 | db | #dba
| db1080 | db | #dba
| db1079 | db | #dba
| db1075 | db | #dba
| db1074 | db | #dba
| ms-be1019 | ms-be |
| es1011 |
| an-worker1078 | analytics | #analytics