This task will track the setup and installation of 6 new ms-be hosts ordered via T228461.
Hostnames: ms-be105[1-6].eqiad.wmnet
Racking Proposal: 10G racks, 2x hosts in rows A+C+D and 3x in row B to refresh old hw. Rack diversity with existing ms-be hw is preferred but not required.
Networking/Subnet/VLAN/IP: Internal subnet per row
Partitioning/Raid: use existing ms-be setup
ms-be1051:
[x] - receive in system on #procurement task T228461
[x] - rack system with proposed racking plan (see above) & update netbox (include all system info plus location, state of planned)
[] - bios/drac/serial setup/testing - system is currently not responsive to ping/ssh on mgmt.
[x] - mgmt dns entries added for both asset tag and hostname
[x] - network port setup (description, enable, vlan)
** end on-site specific steps
[x] - production dns entries added
[] - operations/puppet update (install_server at minimum, other files if possible)
[] - OS installation
[] - puppet accept/initial run (with role:spare)
[] - host state in netbox set to staged
[] - handoff for service implementation
[] - service implementer changes from 'staged' status to 'active' status in netbox'
ms-be1052:
[x] - receive in system on #procurement task T228461
[x] - rack system with proposed racking plan (see above) & update netbox (include all system info plus location, state of planned)
[x] - bios/drac/serial setup/testing
[x] - mgmt dns entries added for both asset tag and hostname
[x] - network port setup (description, enable, vlan)
** end on-site specific steps
[x] - production dns entries added
[x] - operations/puppet update (install_server at minimum, other files if possible)
[] - OS installation
[] - puppet accept/initial run (with role:spare)
[] - host state in netbox set to staged
[] - handoff for service implementation
[] - service implementer changes from 'staged' status to 'active' status in netbox'
ms-be1053:
[x] - receive in system on #procurement task T228461
[x] - rack system with proposed racking plan (see above) & update netbox (include all system info plus location, state of planned)
[x] - bios/drac/serial setup/testing
[x] - mgmt dns entries added for both asset tag and hostname
[x] - network port setup (description, enable, vlan)
** end on-site specific steps
[x] - production dns entries added
[x] - operations/puppet update (install_server at minimum, other files if possible)
[] - OS installation
[] - puppet accept/initial run (with role:spare)
[] - host state in netbox set to staged
[] - handoff for service implementation
[] - service implementer changes from 'staged' status to 'active' status in netbox'
ms-be1054:
[x] - receive in system on #procurement task T228461
[x] - rack system with proposed racking plan (see above) & update netbox (include all system info plus location, state of planned)
[x] - bios/drac/serial setup/testing
[x] - mgmt dns entries added for both asset tag and hostname
[x] - network port setup (description, enable, vlan)
** end on-site specific steps
[x] - production dns entries added
[x] - operations/puppet update (install_server at minimum, other files if possible)
[] - OS installation
[] - puppet accept/initial run (with role:spare)
[] - host state in netbox set to staged
[] - handoff for service implementation
[] - service implementer changes from 'staged' status to 'active' status in netbox'
ms-be1055:
[x] - receive in system on #procurement task T228461
[x] - rack system with proposed racking plan (see above) & update netbox (include all system info plus location, state of planned)
[] - bios/drac/serial setup/testing - responsive to ssh on mgmt, but wrong password set and cannot login
[x] - mgmt dns entries added for both asset tag and hostname
[x] - network port setup (description, enable, vlan)
** end on-site specific steps
[x] - production dns entries added
[] - operations/puppet update (install_server at minimum, other files if possible)
[] - OS installation
[] - puppet accept/initial run (with role:spare)
[] - host state in netbox set to staged
[] - handoff for service implementation
[] - service implementer changes from 'staged' status to 'active' status in netbox'
ms-be1056:
[x] - receive in system on #procurement task T228461
[x] - rack system with proposed racking plan (see above) & update netbox (include all system info plus location, state of planned)
[x] - bios/drac/serial setup/testing
[x] - mgmt dns entries added for both asset tag and hostname
[x] - network port setup (description, enable, vlan)
** end on-site specific steps
[x] - production dns entries added
[x] - operations/puppet update (install_server at minimum, other files if possible)
[] - OS installation
[] - puppet accept/initial run (with role:spare)
[] - host state in netbox set to staged
[] - handoff for service implementation
[] - service implementer changes from 'staged' status to 'active' status in netbox'