This task is to track the receiving, racking, and implementation of a new scs console to replace scs-a8-eqiad.
[X] - receive in scs console via T228202
[X] - add to netbox as 'future-scs-a8-eqiad' and put it as state planned.
[] - test all existing scs connections before you start work, best to know it all works before you change things.
[] - document any cable connections that do not use adapters, as they will need to be re-crimped per T228919#5913768
[] - backup/copy down the scs cable labels to port numbering and then wipe/clear/reset to factory the old scs console.
[] - unrack existing scs-a8-eqiad and rename it to its asset tag, change status to offline
[] - rack new scs console, update its netbox name to scs-a8-eqiad and use all the same network settings as the old scs console
[] - re-attach all connections, keeping in mind you will need to remove any cat5 inline adapters as the SCS console new versions just use standard network cables (no odd pin out.)
[] - test every single connection, repair any broken connections.
[] - update netbox with each connection, info, cable #, etc.