This task will track/coordinate the work between #ops-eqiad and #netops to upgrade the new row D switch stack to have 3 10G switches, rather than just 2. Row D should be made to match the other rows in the setup of (5) 1G racks and (3) 10G racks.
[x] receive in switches off T195451 - https://netbox.wikimedia.org/dcim/devices/855/
[] receive in cables on yet unmade #procurement task for cabling to join these switches in (may need SFP-T, should be able to use existing EX4300 stacking cables
In maintenance window, preferably during a DC failover as row recabling can bring temporary instability:
[] schedule downtime for all systems in row
[] recable asw2-d-eqiad to match official leaf/spine diagram
[] replace asw2-d4-eqiad (EX) with asw3-d4-eqiad (QFX)
[] return all affected servers into service