Create instrumentation to measure the items listed in the parent ticket.
== Questions and metrics
The high level questions and related metrics are in T307571
== Next steps in data process (bolding indicates step we are currently on):
- PM and Data Analyst coordinate to identify research questions, hypotheses, and guardrails for the new feature and associated metrics. This can be done in a measurement plan or on a phabricator ticket depending on the scale of the project.
- Data analyst creates a list of events that need to be tracked to calculate each metric.
- Engineers review the event list and comment on whether we’re already tracking with existing instruments and if new instrumentation is required. New tickets created for any new instrumentation needed. **
- **Data analyst works with engineers to figure out what the new instrumentation should look like and where to store the events. **
- Data analyst documents all of the above in the instrumentation spec
- PM signs off on the plan
== Documentation
[[ https://docs.google.com/spreadsheets/d/1drMnPt8mJa8rQRNCCpgkOo_0eQmdDlHDQnLIbjg8syU/edit#gid=0 | Quickview Panel Instrumentation ]] (WIP)