This task will track the migration of the ps1 and ps2 to be replaced with new PDUs in rack [[ https://netbox.wikimedia.org/dcim/racks/10/ | B2-eqiad ]].
Each server & switch will need to have potential downtime scheduled, since this will be a live power change of the PDU towers.
These racks have a single tower for the old PDU (with and A and B side), with the new PDUs having independent A and B towers.
[] - schedule downtime for the entire list of switches and servers.
[] - Wire up one of the two towers, energize, and relocate power to it from existing/old pdu tower (now de-energized).
[] - confirm entire list of switches, routers, and servers have had their power restored from the new pdu tower
[] - Once new PDU tower is confirmed online, move on to next steps.
[] - Wire up remaining tower, energize, and relocate power to it from existing/old pdu tower (now de-energized).
[] - confirm entire list of switches, routers, and servers have had their power restored from the new pdu tower
== List of routers, switches, and servers ==
| device | role | SRE team coordination | notes
| asw2-b2-eqiad | asw | @ayounsi
| db1072 | db | #dba
| ms-be1020 | ms-be | @fgiunchedi | poweroff / poweron
| cloduvirt1002 | cloudvirt | #cloud-services-team
| cloudvirt1001 | cloudvirt | #cloud-services-team
| cloudvirt1024 | cloudvirt | #cloud-services-team
| cloudvirt1018 | cloudvirt | #cloud-services-team
| cloudvirt1012 | cloudvirt | #cloud-services-team
| cloudvirt1009 | cloudvirt | #cloud-services-team
| cloudvirt1015 | cloudvirt | #cloud-services-team
| cloudvirt1008 | cloudvirt | #cloud-services-team
| db1099 | db | #dba
| ms-be1047 | ms-be | @fgiunchedi | poweroff / poweron
| cloudvirtan1002 | cloudvirtan | #cloud-services-team
| cloudvirtan1001 | cloudvirtan | #cloud-services-team
| an-worker1084 | | #analytics
| an-worker1083 | | #analytics
| cloudelastic1002 | cloudelastic | #cloud-services-team
| cp1080 | cp | #traffic
| cp1079 | cp | #traffic
| analytics1072 | | #analytics