This task will track the racking, setup, of new management switches received in T251580
Row A
[x] - msw-a1-codfw July 2nd
[x] - msw-a2-codfw July 2nd
[x] - msw-a3-codfw July 2nd
[x] - msw-a4-codfw July 2nd
[x] - msw-a5-codfw July 7th
[x] - msw-a6-codfw July 7th
[x] - msw-a7-codfw July 7th
[x] - msw-a8-codfw July 7th
Row B
[] - msw-b1-codfw July 9th
[] - msw-b2-codfw July 9th
[] - msw-b3-codfw July 9th
[] - msw-b4-codfw July 9th
[] - msw-b5-codfw July 14th
[] - msw-b6-codfw July 14th
[] - msw-b7-codfw July 14th
[] - msw-b8-codfw July 14th
Row C
[] - msw-c1-codfw July 16th
[] - msw-c2-codfw July 16th
[x] - msw-c3-codfw June 9th
[] - msw-c4-codfw July 16th
[] - msw-c5-codfw July 16th
[] - msw-c6-codfw July 21st
[] - msw-c7-codfw July 21st
[] - fmsw-c8-codfw July 21st
Row D
[] - msw-d1-codfw July 21st
[] - msw-d2-codfw July 23rd
[] - msw-d3-codfw July 23rd
[] - msw-d4-codfw July 23rd
[] - msw-d5-codfw July 23rd
[] - msw-d6-codfw July 28th
[] - msw-d7-codfw July 28th
[] - msw-d8-codfw July 28th