Please note these systems were ordered on T231255, and #dc-ops needs feedback from #serviceops on the split between mw, kubenetes, thumbor, & wtp systems ordered on that task.
#serviceops: Please update this task to denote how many of the 106 total systems are to be split between mw, kubenetes, thumbor, & wtp. Once we have that info, 3 additional tasks can be filed for kubernetes, thumbor, and wtp.
Racking Proposal:
|Row |A |B |C |D|
|mw servers |19 |25| 31 |11|
Hostnames: mw2[291-2377].codfw.wmnet
This checklist should be duplicated for EVERY SINGLE HOST:
[x] - receive in system on #procurement task T231255
[x] - rack system with proposed racking plan (see above) & update netbox (include all system info plus location, state of planned):
[x] - bios/drac/serial setup/testing :
[] - mgmt dns entries added for both asset tag and hostname only servers in rack B3 ,B6, A3 ,A6, D3,C6
[] - network port setup (description, enable, vlan)
** end on-site specific steps
[] - production dns entries added : only servers in rack B3 ,B6, A3,A6,D3,C6
[] - operations/puppet update (install_server at minimum, other files if possible)
[] - OS installation
[] - puppet accept/initial run (with role:spare)
[] - host state in netbox set to staged
[] - handoff for service implementation
[] - service implementer changes from 'staged' status to 'active' status in netbox'