This task will track the racking, setup, and dc ops deployment of the new switches for rows E & F in the new cage/expansion.
This is not a typical racking task, due to the nature of this deployment. While this task initially has info for both rows E and F, row F may be moved to another task later as its expansion/buildout is after row E.
== Hostnames ==
Hostnames will need to be reviewed by #netops, as we've not used dedicated spine switches in the past. The current assumption will be 'spine-rack-eqiad' once the location of the spine switches are decided on T291485#7375305
== Cabling Plan / Diagrams ==
#netops to provided detailed directions in this section on the cabling diagram/plan for the routing of cables and uplinks between racks. This cannot be fully provided until a decision is made on spine switch placements.
== Per host setup checklist ==
The below checklist has all the steps required for each switch to be brought online by #dc-ops for #netops configuration and deployment.
ssw1-e1-eqiad (QFX5120-32C-AFI):
[x] - receive in system on #procurement task T287591 & in coupa
[x] - rack into assigned rack, spine switch rack and hostnames will be determined later. Example: If it goes into E2 and E7, then it would be spine-e2-eqiad and spine-e7-eqiad.)
[x] - label and power up switch
[x] - connect new switch to a port on the scs
[] - test scs connection and verify connectivity
[] - see Cabling Plan section above for how to connect to rest of the row, connect as advised
ssw1-f1-eqiad (QFX5120-32C-AFI):
[x] - receive in system on #procurement task T287591 & in coupa
[x] - rack into assigned rack, spine switch rack and hostnames will be determined later. Example: If it goes into E2 and E7, then it would be spine-e2-eqiad and spine-e7-eqiad.)
[x] - label and power up switch
[] - connect new switch to a port on the scs
[] - test scs connection and verify connectivity
[] - see Cabling Plan section above for how to connect to rest of the row, connect as advised
lsw-e1-eqiad (QFX5120-48Y-AFI):
[x] - receive in system on #procurement task T287591 & in coupa
[x] - rack into assigned rack (see hostname of switch for non spines) and enter switch into netbox with all associated information
[x] - label and power up switch
[x] - connect new switch to a port on the scs
[x] - test scs connection and verify connectivity
[x] - see Cabling Plan section above for how to connect to rest of the row, connect as advised
lsw-e2-eqiad (QFX5120-48Y-AFI):
[x] - receive in system on #procurement task T287591 & in coupa
[x] - rack into assigned rack (see hostname of switch for non spines) and enter switch into netbox with all associated information
[x] - label and power up switch
[x] - connect new switch to a port on the scs
[x] - test scs connection and verify connectivity
[x] - see Cabling Plan section above for how to connect to rest of the row, connect as advised
lsw-e3-eqiad (QFX5120-48Y-AFI):
[x] - receive in system on #procurement task T287591 & in coupa
[x] - rack into assigned rack (see hostname of switch for non spines) and enter switch into netbox with all associated information
[x] - label and power up switch
[x] - connect new switch to a port on the scs
[x] - test scs connection and verify connectivity
[x] - see Cabling Plan section above for how to connect to rest of the row, connect as advised
cloudsw1-e4-eqiad (QFX5120-48Y-AFI):
[x] - receive in system on #procurement task T287591 & in coupa
[x] - rack into assigned rack (see hostname of switch for non spines) and enter switch into netbox with all associated information
[x] - label and power up switch
[x] - connect new switch to a port on the scs
[x] - test scs connection and verify connectivity
[x] - see Cabling Plan section above for how to connect to rest of the row, connect as advised
lsw-f1-eqiad (QFX5120-48Y-AFI):
[x] - receive in system on #procurement task T287591 & in coupa
[x] - rack into assigned rack (see hostname of switch for non spines) and enter switch into netbox with all associated information
[x] - label and power up switch
[x] - connect new switch to a port on the scs
[x] - test scs connection and verify connectivity
[x] - see Cabling Plan section above for how to connect to rest of the row, connect as advised
lsw-f2-eqiad (QFX5120-48Y-AFI):
[x] - receive in system on #procurement task T287591 & in coupa
[x] - rack into assigned rack (see hostname of switch for non spines) and enter switch into netbox with all associated information
[x] - label and power up switch
[x] - connect new switch to a port on the scs
[x] - test scs connection and verify connectivity
[x] - see Cabling Plan section above for how to connect to rest of the row, connect as advised
lsw-f3-eqiad (QFX5120-48Y-AFI):
[x] - receive in system on #procurement task T287591 & in coupa
[x] - rack into assigned rack (see hostname of switch for non spines) and enter switch into netbox with all associated information
[x] - label and power up switch
[x] - connect new switch to a port on the scs
[x] - test scs connection and verify connectivity
[x] - see Cabling Plan section above for how to connect to rest of the row, connect as advised
cloudsw1-f4-eqiad (QFX5120-48Y-AFI):
[x] - receive in system on #procurement task T287591 & in coupa
[x] - rack into assigned rack (see hostname of switch for non spines) and enter switch into netbox with all associated information
[x] - label and power up switch
[x] - connect new switch to a port on the scs
[x] - test scs connection and verify connectivity
[x] - see Cabling Plan section above for how to connect to rest of the row, connect as advised
**TODO: duplicate the above checklist for row F, or create a new task for Row F. Do not resolve this task without doing one of these.**