This task will track the racking, setup, and installation of mwmaint1002.eqiad.wmnet.
Please note that mwmaint1001.eqiad.wmnet was a temporary reallocation of an image scaler. Once this new host is fully online and in service, a new task needs to be created (or existing linked) to track the return/reimage of mwmaint1001 back to image scaler duties.
Racking Proposal: Any 1G rack will do, this will have an internal vlan/ip.
mwmaint1002:
[] - receive in system on #procurement task T195418
[] - rack system with proposed racking plan (see above) & update racktables (include all system info plus location)
[] - bios/drac/serial setup/testing
[] - mgmt dns entries added for both asset tag and hostname
[] - network port setup (description, enable, vlan)
** end on-site specific steps
[] - production dns entries added
[] - operations/puppet update (install_server at minimum, other files if possible)
[] - OS installation
[] - puppet accept/initial run
[] - handoff for service implementation