rack & on-site setup of cp2001-cp2026
Closed, ResolvedPublic

Description

The racking/stacking task will be set for cp2001-cp2026 via this task. However, it is currently assgined to @RobH until we get @mark & @BBlack to sign off on the proposed layout/load distribution.

I'd assume we would want to quantity balance these across all 4 rows, in the 10G racks. So that is rack 2 and 7 in each row. Since rows A-C already have items in racks 2 & 7, I'd suggest putting the extra 2 servers in row D.

My proposed layout is thus:

cp2001: a2
cp2002: a2
cp2003: a2
cp2004: a7
cp2005: a7
cp2006: a7
cp2007: b2
cp2008: b2
cp2009: b2
cp2010: b7
cp2011: b7
cp2012: b7
cp2013: c2
cp2014: c2
cp2015: c2
cp2016: c7
cp2017: c7
cp2018: c7
cp2019: d2
cp2020: d2
cp2021: d2
cp2022: d2
cp2023: d7
cp2024: d7
cp2025: d7
cp2026: d7

If this is acceptable, I'll update this task and assign to Papaul. When assigned to him, it will include the following items:

  • - receive in servers normally per processes in RT (linked off T98005)
  • - rack cp2001-cp2026 in the racks listed above
  • - update mgmt dns in repo for the new cp mgmt entries (feel free to add @RobH for review/merge); ensure mgmt dns entries include both hostname.mgmt and servicetag.mgmt.
  • - update this task listing each system's network port (which is plugged into the 10G switch via the DAC cables, not fiber optic patches)
  • - add systems to racktables, including RT info and service tag info (should already be completed as part of receiving systems)
  • - update racktables for each system rack location
  • - update bios setttings for use
  • - update drac settings for use
  • - test serial console redirection/drac ssh connectivity
  • - Additionally, each system has to have the HDDs removed and replaced with the SSDs we ordered. We want to install two of the SSDs into each of these systems. The order for these was on the same RT ticket.

Related Objects

Event Timeline

RobH claimed this task.
RobH raised the priority of this task from to Needs Triage.
RobH updated the task description. (Show Details)
RobH added a project: acl*sre-team.
RobH added a subtask: Restricted Task.
RobH added subscribers: Papaul, BBlack, RobH and 2 others.

Seems ok to me for physical layout.

BIOS settings are standard, but note that we really really care about having Logical Processor and IPMI enabled, Virtualization disabled, and Power Mgmt to Performance (which are all standard, I think!)

BBlack triaged this task as Medium priority.Jun 3 2015, 1:52 PM
BBlack added a project: Traffic.
BBlack set Security to None.
BBlack moved this task from Backlog to Upcoming on the Traffic board.

I'm assigning this to @mark for his approval of the layout. Once he approves, this can be tasked to @Papaul.

Rack tables up to date
servers rack complete
physical label in place
replacement of 250 GB SATA drives with 400 GB SSD drives complete on all servers

will start the the cabling process, BIOS and mgmt setup after lunch

I talked to @mark about this, we're good on layout (sounds like it was progressing anyways).

RobH closed subtask Restricted Task as Resolved.Jun 10 2015, 6:36 PM

cabling complete
mgmt and BIOS setting complete
Test complete

cp2001 = 10.193.2.172 44:A8:42:2D:20:1D port Xe-2/0/3
cp2002 = 10.193.2.173 44:A8:42:2D:0E:E6 port Xe-2/0/5
cp2003 = 10.193.2.174 44:A8:42:2D:05:76 port Xe-2/0/6
cp2004 = 10.193.2.175 44:A8:42:2D:0E:24 port Xe-7/0/3
cp2005 = 10.193.2.176 44:A8:42:2D:15:7B port Xe-7/0/5
cp2006 = 10.193.2.177 44:A8:42:2D:00:29 port Xe-7/0/6
cp2007 = 10.193.2.178 44:A8:42:2D:10:58 port Xe-2/0/3
cp2008 = 10.193.2.179 44:A8:42:2D:15:31 port Xe-2/0/5
cp2009 = 10.193.2.180 44:A8:42:2D:14:D3 port Xe-2/0/6
cp2010 = 10.193.2.181 44:A8:42:2D:18:CE port Xe-7/0/3
cp2011 = 10.193.2.182 44:A8:42:2D:11:BD port Xe-7/0/4
cp2012 = 10.193.2.183 44:A8:42:2D:15:01 port Xe-7/0/5
cp2013 = 10.193.2.184 44:A8:42:2C:F5:9A port Xe-2/0/3
cp2014 = 10.193.2.185 44:A8:42:2C:F5:8E port Xe-2/0/4
cp2015 = 10.193.2.186 44:A8:42:2C:E3:FA port Xe-2/0/5
cp2016 = 10.193.2.187 44:A8:42:2D:03:39 port Xe-7/0/3
cp2017 = 10.193.2.188 44:A8:42:2D:0E:18 port Xe-7/0/4
cp2018 = 10.193.2.189 44:A8:42:2D:0A:0F port Xe-7/0/5
cp2019 = 10.193.2.190 44:A8:42:2D:1E:50 port Xe-2/0/0
cp2020 = 10.193.2.191 44:A8:42:2D:00:DB port Xe-2/0/1
cp2021 = 10.193.2.192 44:A8:42:2D:20:05 port Xe-2/0/2
cp2022 = 10.193.2.193 44:A8:42:2D:1E:80 port Xe-2/0/3
cp2023 = 10.193.2.194 44:A8:42:2D:05:3C port Xe-7/0/0
cp2024 = 10.193.2.195 44:A8:42:2D:1D:3C port Xe-7/0/1
cp2025 = 10.193.2.196 44:A8:42:2D:14:DF port Xe-7/0/2
cp2026 = 10.193.2.197 44:A8:42:2D:1C:87 port Xe-7/0/3