Codfw:row A/B: rack/cable new switches
Closed, ResolvedPublic

Description

This task will tacking the racking and cabling of the new switches in Codfw

Switchrackedpowermgmtconsolessw1-a1-leaf linkssw1-a8-leaf linkcr-spine link
ssw-a1YESYESYESYESYESYESYES
ssw-a8YESYESYESYESYESYESYES
lsw-a1YESYESYESYESYES
lsw-a2YESYESYESYESYES
lsw-a3YESYESYESYESYES
lsw-a4YESYESYESYESYES
lsw-a5YESYESYESYESYES
lsw-a6YESYESYESYESYES
lsw-a7YESYESYESYESYES
lsw-a8YESYESYESYESYES
lsw-b2YESYESYESYESYES
lsw-b3YESYESYESYESYES
lsw-b4YESYESYESYESYES
lsw-b5YESYESYESYESYES
lsw-b6YESYESYESYESYES
lsw-b7YESYESYESYESYES
lsw-b8YESYESYESYESYES

Event Timeline

Papaul triaged this task as Medium priority.Apr 19 2023, 3:09 PM
Papaul updated the task description. (Show Details)
Papaul closed this task as Resolved.EditedJun 16 2023, 12:35 AM

@cmooney @ayounsi the cabling is done.I am using port 55 on each leaf to connect to ssw1-a1 and pot 54 to connect to ssw1-a8.
the last port on each spine is connected to cr*(1/5)
lsw1-a1 et-0/0/55 is connected to ssw1-a1 et-0/0/0
lsw1-a2 et-0/0/55 is connected to ssw1-a1 et-0/0/1
....
....

lsw1-a8 et-0/0/55 is connected to ssw1-a1 et-0/0/7
lsw1-b2 et-0/0/55 is connected to ssw1-a1 et-0/0/8
....

lsw1-b8 et-0/0/55 is connected to ssw1-a1 et-0/0/14

the same above is true for ssw1-a8

Thanks @Papaul great work!

So it seems I was wrong we can run homer on these without having to add anything to devices.yaml for now. Just need to set to 'active' in Netbox and run Homer.

I did that and it worked fine on ssw1-a1-codfw. Unfortunately for the others it didn't work. The Leaf switches all failed as follows:

Type "yes" to commit, "no" to abort.
> yes
INFO:homer.transports.junos:Committing the configuration on lsw1-b8-codfw.mgmt.codfw.wmnet
ERROR:homer:Failed to commit on lsw1-b8-codfw.mgmt.codfw.wmnet: Commit error: 
configuration check-out failed

ERROR:homer:Homer run had issues on 14 devices: ['lsw1-a1-codfw.mgmt.codfw.wmnet', 'lsw1-a2-codfw.mgmt.codf.....................

ssw1-a8-codfw caused a bit of an issue at first, I realised as it's the one me and volans were testing before and as a result had the old RSA key for the homer user. Fixed that via console at it was fine.

I've set all back to 'planned' in Netbox for now. Will need to investigate what the Leaf switches don't like.