[Sprint 08 Goal] SDS 2.5 Create implementation plan to capture Metrics Platform baselines
Closed, ResolvedPublic

Description

Description

As a way to measure the Metrics Platform's progress in achieving our goals, we determined a set of measurable success criteria:

  • decrease the time to data by X%
  • decrease the number of custom fields across instruments by X%
  • decrease the amount of engineering days steps required to create instruments by X%

We now need to establish tooling or processes to collect this information in an ongoing way as well as establish baselines

User Story

As the Data Products Product Manager
I need to explore data about the current baselines for product team Experiment Owners to get data from beginning to end of the instrumentation process
so I can set achievable goals, establish realistic expectations for our work, and have a starting point from which to tell the story of our team's journey.

As a Senior Product + Tech Leader
I need to view visualized trustworthy empirical data about what the current problems are
so I can ensure we are prioritizing high impact efforts that can produce a reasonable return on investment (ROI)

Outcome

We know at the beginning of the fiscal year:

  • How long it takes until Data Analysts can access the data from instruments (time to data)
  • How many custom fields exist across all active instruments
  • How long it took engineers to create instruments on average across all instruments

And we can easily find out the same data at the end of fiscal year Q1, Q2, and into the future at a quarterly basis.

Event Timeline

VirginiaPoundstone renamed this task from [SPRINT GOAL 05] Capture Metrics Platform baselines to [SPRINT 05 GOAL] Capture Metrics Platform baselines.Jan 10 2024, 4:19 PM
VirginiaPoundstone renamed this task from [SPRINT 05 GOAL] Capture Metrics Platform baselines to [SPRINT 08 GOAL] Capture Metrics Platform baselines.Jan 12 2024, 6:15 PM
VirginiaPoundstone updated the task description. (Show Details)
VirginiaPoundstone renamed this task from [SPRINT 08 GOAL] Capture Metrics Platform baselines to [Sprint 08 Goal] Capture Metrics Platform baselines.Jan 12 2024, 6:28 PM
VirginiaPoundstone renamed this task from [Sprint 08 Goal] Capture Metrics Platform baselines to [Sprint 08 Goal] SDS 2.5 Capture Metrics Platform baselines.
VirginiaPoundstone renamed this task from [Sprint 08 Goal] SDS 2.5 Capture Metrics Platform baselines to [Sprint 09 Goal] SDS 2.5 Capture Metrics Platform baselines.Jan 22 2024, 1:29 PM
VirginiaPoundstone lowered the priority of this task from High to Low.Jan 22 2024, 1:58 PM
phuedx renamed this task from [Sprint 09 Goal] SDS 2.5 Capture Metrics Platform baselines to [Sprint 08 Goal] SDS 2.5 Create implementation plan to capture Metrics Platform baselines.Jan 22 2024, 2:37 PM
phuedx raised the priority of this task from Low to High.
phuedx added a project: Goal.