Let's track progress on the migration of this team to Phabricator.
- @Spage (Scrum master), @DannyH (Product Manager), @Quiddity (community liaison, bug filer extraordinaire)
- Flow team has a Flow — backlog board. Every two-week sprint we moves tasks to a current iteration board we rename Flow — Sprint Y and move Done tasks to a new Sprint X column in the Flow — previous sprints board
- (optional) Have you scheduled a team meeting with @Qgil to discuss the migration? (yyyy-mm-dd)
- Blockers of the migration identified: (list the task numbers between {curly brackets})
- Planned date for the migration/creation of a first real project: our sprint after bugs are migrated.
- Do you plan to have all your projects moved by the end of 2014? Yes
(...)
- More than half of our team members and ongoing sprints are working in Phabricator now (2014-12-09)
- All our projects have been moved to Phabricator. Mission completion! (yyyy-mm-dd)