TEC3:O3:O3.1:Q3 Goal - Move cxserver, citoid, changeprop, eventgate (new service) and ORES (partially) through the production CD Pipeline
Closed, InvalidPublic

Event Timeline

greg triaged this task as Medium priority.Jan 2 2019, 7:18 PM
greg created this task.
greg renamed this task from TEC3:O3:O3.1:Q3 Goal - Move cxserver, citoid, changeprop, and ORES (partially) through the production CD Pipeline to TEC3:O3:O3.1:Q3 Goal - Move cxserver, citoid, changeprop, eventgate (new service) and ORES (partially) through the production CD Pipeline.Jan 2 2019, 7:21 PM

When discussing this before, I think we've had the cpjobqueue in planning as well? It should be a really easy move since the codebase is shared with change-prop. However, given the importance of the job queue compared to change-prop, maybe it is indeed wise to delay it to a next quarter.

thcipriani subscribed.

All services except for ORES through the pipeline, task no longer makes sense as written, this is cleanup.